Read the whole article here. John goes on to mention that a fourth tower could eventually become a reality.Crews were busy Saturday erecting a third 160-foot tall demethanizer tower at the 170-acre UEO (Utica East Ohio) Kensington Plant.Baron John, construction manager for UEO, said over two months of preparation went into Saturday's effort, and the tower took two hours to build. "We had 20 people, and used smaller cranes with maximizers for extra weights as the tower was raised," John said.After freezing temperatures kept workers inside Monday and Tuesday, preparation resumed Wednesday. Just as the crew was about to raise the tank, however, the weather forced another change of plans.